Trigger levels depend on tunnel geometry, geology, overburden, support system, expected ground behaviour, design analysis, construction stage, baseline movement, and the approved method statement. Enter the values from the project's approved TARP / design — not generic defaults.
Zone overrides: enter a chainage (e.g. 0+685) and load. A zone override only replaces the fields you change — others inherit the project values.
Observational triggers (loose fall, rib buckling, cracking + movement) are not threshold-based and always override numerical values, per Step 15.
Data freshness is itself monitored: if the last reading is older than the configured limit, TARP degrades to AMBER — "safety status unconfirmed" (Step 17).
ITA guidance — monitoring layout and interpretation based on predicted ground/structural mechanism and critical areas, not generic instrumentation · Spec Module 2, Steps 14–17